A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?
- 10%
- (50/3)%
- 20%
- 25%
Answer
(c) 20%
Explanation
Men × days is constant: M × 6k = M′ × 5k ⇒ M′ = 6M/5 = 1.2M.
Increase = 20%.
← Question 6 – In the expression 5 * 4 * 3 * 2 * 1, * is chosen from +, −, × each at most two times. What is the smallest…
Question 8 → – X, Y and Z can complete a piece of work individually in 6 hours, 8 hours and 8 hours respectively. However, only one…
All 80 questions of the UPSC CSAT 2024 Question Paper with answers
More Basic numeracy & data interpretation questions from this paper
- Q6 – In the expression 5 * 4 * 3 * 2 * 1, * is chosen from +, −, × each at most two times. What is the smallest…
- Q8 – X, Y and Z can complete a piece of work individually in 6 hours, 8 hours and 8 hours respectively. However, only one…
- Q9 – How many consecutive zeros are there at the end of the integer obtained in the product 1² × 2⁴ × 3⁶ × 4⁸ × … × 25⁵⁰?
- Q10 – On January 1st, 2023, a person saved ₹1. On January 2nd, 2023, he saved ₹2 more than that on the previous day. On…
- Q15 – 222³³³ + 333²²² is divisible by which of the following numbers?
- Q16 – What percent of water must be mixed with honey so as to gain 20% by selling the mixture at the cost price of honey?