A man completes 7/8 of a job in 21 days. The total amount of work is then increased by 50%. How many additional days will he need to finish it at the same rate?

  1. 24
  2. 21
  3. 18
  4. 15

Answer

(d) 15

Explanation

Completing the original work would take 24 days. Increasing total work by 50% makes it 36 days of work; 21 days are done, leaving 15 days.

← Question 79 – A number multiplied by 7 gives a number consisting only of ones (1111...). What is the smallest possible original…

All 80 questions of the UPSC CSAT 2021 Question Paper with answers

More Basic numeracy & data interpretation questions from this paper

  1. Q79 – A number multiplied by 7 gives a number consisting only of ones (1111...). What is the smallest possible original…
  2. Q78 – A price decreases by 20% and is then increased by 25% of its new value. What is the net percentage change?
  3. Q77 – X tells Y: “At the time of your birth I was twice as old as you are at present.” X is now 42. Which statements are…
  4. Q76 – A two-digit number and the number obtained by reversing its digits differ by 54. Which statements are true? 1. The sum…
  5. Q74 – A pie chart describes body components: protein 16%, water 70%, and other dry elements the rest. If protein plus other…
  6. Q70 – A sum is divided among A, B and C in ratio p:q:r. Which statements are true? 1. A gets the most if p > q+r. 2. C gets…