Either 3 men or 7 women finish a job in 32 days. How long do 7 men and 5 women take to complete twice the job?
- 19 days
- 21 days
- 27 days
- 36 days
Answer
(b) 21 days
Explanation
1 कार्य = 3×32=96 पुरुष-दिन; 5 महिलाएँ =15/7 पुरुष; 7+15/7=64/7 पुरुष; 2 कार्य समय=192÷(64/7)=21 दिन.
← Question 93 – Arrange the stages: 1 Presentation; 2 Recommendation; 3 Arrival; 4 Discussion; 5 Introduction.
Question 95 → – Trains of lengths 127 m and 98 m travel in opposite directions at 35 and 55 km/h. Time to cross each other?
All 100 questions of the UPPSC PCS CSAT 2020 Question Paper with answers
More Basic numeracy & data interpretation questions from this paper
- Q95 – Trains of lengths 127 m and 98 m travel in opposite directions at 35 and 55 km/h. Time to cross each other?
- Q98 – A 112 m × 62 m field has a cubical pit of side 6 m at each of four corners. All dug soil is spread on the remaining…
- Q99 – A metal sphere has radius 3 cm. What length of wire of diameter 4 mm can be drawn from it?
- Q100 – Seventeen candidates appeared. Ten candidates failed with marks 10, 9, 6, 7, 8, 8, 7, 5, 4, 6. Find the median score…
- Q78 – A monkey climbs a 12 m slippery pole, climbing 2 m in a minute and sliding 1 m in the next minute. How long to reach…